Tuesday, August 27, 2019
New Construction (Locations to be Determined)
- Fairfax/Oakton Area elementary school (construction) $35,330,490
- Silver Line elementary school (planning) $2,007,500
New Construction Subtotal: $37,337,990
Capacity Enhancement (Additions and other modifications)
- Relocation of 1 Modular Addition $2,000,000
- West Potomac High School Addition (construction) $22,298,143
- Justice High School Addition (construction) $14,595,641
- Madison High School Addition (construction) $19,543,731
Capacity Enhancement Subtotal: $58,437,515
Elementary School Renovation
- Hybla Valley (construction) $27,302,053
- Washington Mill (construction) $28,727,060
- Braddock (construction) $33,039,232
- Fox Mill (construction) $28,379,862
- Oak Hill (construction) $33,497,669
- Wakefield Forest (planning) $1,172,318
- Louise Archer (planning) $1,728,657
- Crossfield (planning) $1,416,325
- Mosby Woods (planning) $1,717,009
- Bonnie Brae (planning) $1,615,034
Elementary School Renovation Subtotal: $158,595,219
Middle School Renovation
- Cooper (construction) $49,660,553
- Frost (construction) $53,468,723
Middle School Renovation Subtotal: $103,129,276
Project Subtotal $357,500,000
Bond Cost $2,500,000
REFERENDUM TOTAL $360,000,000